Emerald Parkway Phase 8 and Riverside Drive – Expect traffic delays

Beginning Tuesday, October 21, traffic loops are scheduled to be installed in the asphalt. Expect traffic delays at the intersection Tuesday through Friday, between 8 a.m. and 3 p.m. each day.
Continue Reading →

Muirfield Drive Bike Lanes and Pedestrian Bridges

The recent rains have delayed the scheduled paving for the Muirfield Drive bike lanes currently under construction. The south bound bike lanes will be paved Saturday and Sunday, October 18 and 19. Traffic will be maintained at all times on Muirfield Drive during the paving operation.
Continue Reading →

Street Maintenance Program

The Street Maintenance Program consists of replacement of deteriorated concrete curb and gutter, street base stabilization, milling of deteriorated pavement surfaces and placement of new asphalt pavement.
Continue Reading →

Hard Road and Riverside Drive

Road and intersection improvements are underway with milling and paving scheduled to begin in the next few days. The new construction will add a northbound right turn lane from Riverside Drive to Hard Road and traffic signal modifications. Lanes are open, but there may be traffic dela
Continue Reading →

Avery Road Paving Project

This quick project is expected to be completed by next Friday, Oct 10. There will be some lane restrictions and traffic delays. Please use caution and add extra time for travel.
Continue Reading →

Dublin Road and Glick Road Widening

The Dublin/Glick Rd. intersection continues to be an active construction site. The completion date has been modified to Wednesday, Nov. 26 due to a delay in utility relocation.
Continue Reading →

New LED Street Light installation in Historic Dublin

New LED street lights and new poles are being installed along Bridge and High Streets this summer in the Historic District.
Continue Reading →

2015 Major Transportation Construction Projects Update Highlights

Series of 2015 construction projects will address some of Dublin’s most significant transportation needs, and will significantly improve accessibility and safety
Continue Reading →

Dublin Road north of Glick Road is now open

Dublin Road north of Glick Road opened at 10 a.m. on Thursday, August 21.
Continue Reading →

Emerald Parkway – Bright Road Update

Beginning the week of July 21 through July 25, 2014, Bright Road will be closed to all traffic where Emerald Parkway crosses Bright Road.
Continue Reading →

Darree Fields Parking Lots

Parking lot paving - Completed
Continue Reading →

Muirfield Village Street Maintenance

Continuing street maintenance work in Kentigern Place on Kentigern Drive and Greenside Drive. Continuing Work on Kilbannon Court, Gailes Court, Turin Hill Court South, scheduled for Monday, July 14 through Friday, July 18, 2014.
Continue Reading →

Sidewalk Maintenance Program

Several neighborhood sidewalks will be repaired this summer and fall starting the week of August 4, 2014.
Continue Reading →

Heather Glen Road Improvements

Street maintenance work is completed.
Continue Reading →

Muirfield Water Line Project 2014

The City of Dublin has funded a capital improvement project to replace and upgrade existing waterlines in your neighborhood. Work will begin the week of July 14, 2014.
Continue Reading →

City of Dublin 2014 Road Improvement Preview

A preview of all Road Improvements scheduled in 2014.
Continue Reading →

Storm Structure Maintenance Program

The Storm Structure Maintenance Program will begin May 30, 2014, and is scheduled to continue through the end of October 2014. Signs will be posted once construction is scheduled to begin. During the construction period through October 15, 2014 – residents may see temporary “No Parkin
Continue Reading →