Water Tank Improvements Project

Project Overview

The City of Dublin is completing maintenance and improvement work at several water towers throughout the community as part of the City’s Capital Improvements Program (CIP). The work will help maintain the reliability and long-term performance of Dublin’s water system.

Additional project details will be added as information becomes available.

Project Locations

Maintenance and inspection work is scheduled at the following water towers:

Dublin Road Water Tower
Tartan West Water Tower
Darree Fields Water Tower
Avery Road Water Tower
Blazer Parkway Water Tower

What to Expect

Residents may notice contractor activity, maintenance vehicles and equipment near water tower sites during scheduled work periods. Water service impacts are not anticipated as part of the project.

Schedule

Dublin Road Water Tower
Tank drawdown begins Oct. 7 or Oct. 9
Improvement work scheduled Oct. 13-16
Inspection Oct. 19
Tank returns to service Oct. 23

Tartan West Water Tower
Tank drawdown begins Oct. 27
Improvement work scheduled Oct. 27-30
Inspection Nov. 2
Tank returns to service Nov. 6

Darree Fields Water Tower
Wash line replacement work Nov. 2-6
Tank drawdown begins Nov. 9
Inspection Nov. 16
Tank returns to service Nov. 20

Avery Road Water Tower
Interior maintenance work scheduled Nov. 9-30
Final inspection Nov. 30

Blazer Parkway Water Tower
Water tower inspection scheduled Dec. 1-5
No contractor improvement work is planned at this location.

Questions? Contact:
City of Dublin Engineering Division
Phone: 614.410.4400

Latest Video

Latest Photos