The City is installing a waterline and shared use path extension along Riverside Drive and Bright Road. The project includes the installation of new water main between Emerald Parkway and Hannah Hills Drive and on Bright Road between Riverside Drive and Grande Cliffs Drive.

The project will also construct a shared use path along the east side of Riverside Drive between Emerald Parkway and the existing path north of Hannah Hills Drive, with a pedestrian bridge over Billingsley Creek.

Residents living west of Riverside Drive will receive a 3” PVC casing pipe to run service laterals under the road.

Improving the infrastructure that serves our City is an investment that adds value and high-quality amenities for residents.

Work begins the week of Feb. 6, 2023, and should be complete in August 2023.

Work Status

  • Construction of new waterline on Riverside Drive between Emerald Parkway and Hanna Hills Drive
  • Final restoration, project mostly complete

Traffic Impact

  • Northbound Riverside Drive lane closures north of Emerald Parkway during working hours

Completion Date

  • August 2023

 