logo


Dublin Drive – Road Improvement Updates

View larger map | Mobile Map | Get The iOS app | Construction Project Inquiry & Service Follow up

The City of Dublin provides a high level of service to its residents and visitors through a variety of improvement projects, including road maintenance, intersection upgrades and multi-use path development. Follow progress with our interactive construction map, updated by engineers and other City employees as projects are underway.

Shared Use Path Program

The City of Dublin maintains its shared use paths with an annual maintenance program. The City has contracted with Chemcote Inc., which plans to start work the week of April 25, 2022. The project is expected to be completed by the end of May. Work is weather dependent, and the schedul
Continue Reading →

Sanitary Sewer Extensions – Trails End Drive

Update: There was a virtual public meeting about this project on April 13, 2022, from 7-8 p.m. Residents affected by the project should have received notification from the City about the meeting: San Sewer Ext Area 1B Public Meeting. Public Meeting: April 13, 2022 Public Meeting: June
Continue Reading →

2022 Street Maintenance Program

The Street Maintenance Program consists of replacement of deteriorated concrete curb and gutter, street base stabilization, milling of deteriorated pavement surfaces and placement of new asphalt pavement.
Continue Reading →

Hayden Run Wall & Fence Repair

Update: Work starts Tuesday, May 31 with tree trimming/removal. The westbound curb lane will be closed off approaching Frantz Rd. This project will see stone wall maintenance and railing replacement on Hayden Run Road. The project is expected to be completed in June 2022.
Continue Reading →

Bridge Park Block G Construction Traffic Impact

  The Block G section of Bridge Park is currently under construction. Here is what Dublin drivers should know when traveling through the area. Traffic Impact: Dale Drive will be closed from Bridge Park Avenue to Tuller Ridge Drive: Tuesday, May 31, from 7 a.m. to 3 p.m. Wednesday
Continue Reading →

Shannon Glen Pedestrian Bridge Replacement

The Shannon Glen Park bridge replacement project is expected to be complete in May 2022. During construction, the bridge and a section of shared use path will be closed for approximately six weeks. Update: The project is effectively complete. Work is weather dependent, and the schedul
Continue Reading →

Deer Run Force Main and Lift Station Project: Dublin Road

Update: No work is scheduled until June 2022. Road signs have begun to be placed along the construction route. The City will be installing a force main sewer system on Dublin Road between Emerald Parkway and Glenaire Drive beginning on June 8, 2022. The project primarily constructs 2.
Continue Reading →

University Boulevard Phase 2 Construction

The University Boulevard Phase 2 project is underway, with installation of public roadway, new concrete curb and traffic signal upgrade. Completion of this project is expected in January 2023. Currently, the project is working on the re-alignment of Shier Rings Road between Eiterman R
Continue Reading →

U.S. 33-S.R. 161-Post Road Interchange Improvements

Project Update: This project is expected to being the week of May 9, 2022 with the installation of temporary pavements on U.S. 33 and S.R. 161.   This rural interchange is at the center of substantial local and regional economic development, and the current configuration does not
Continue Reading →

Spring Hydrant Flushing During the Month of May

Washington Township Fire Department will be conducting its annual spring flushing and pumping of the City’s hydrants (with green bases) during the month of May. Flushing and pumping will take place daily from 8 a.m. to 6 p.m. throughout the City of Dublin. Residents may experience bri
Continue Reading →

Utility Work Starting on Riverside Drive

Utility work continues in the Bridge Park area. Drivers can expect to see lane restrictions on Riverside Drive due to utility work. Expect lane shifts due to cable vehicles accessing manholes, with temporary lane shifts to load/unload equipment. Post-construction restoration work will
Continue Reading →

AEP Dublin West Innovation District Improvements

Update: Matting along pole route has been installed and pole foundations are being drilled and set. Next, new high-voltage transmission lines will be installed from Shier Rings Road power substation to Amlin substation. In affected areas, drivers can expect two to five-minute traffic
Continue Reading →

South High Street Streetscape Enhancements

Progress update: South High Street remains open to southbound and northbound traffic. There should be limited interruptions to on-street parking during normal work hours as crews finalize the streetscape between 7 a.m. and 4 p.m. Southbound South High Street may experience temporary p
Continue Reading →

Maintaining Guardrails

Maintaining guardrails is an important safety priority for the City of Dublin. Guardrail maintenance improvements are planned for the new wood guardrail located at east Bridge Street and Riverside Drive roundabout. Traffic Impact The eastbound Bridge Street curb lane at the Riverside
Continue Reading →

Mooney Street Closure

Portions of Mooney Street will be closed through December 2021.
Continue Reading →

Bright Road 12-Inch Water Main Extension

Update: No work is currently scheduled and there is no anticipated impact to traffic. Work is underway on a water main extension on Bright Road between Emerald Parkway and Sawmill Road. This project is currently in operation and is expected to end May 2022. During the work, Bright Roa
Continue Reading →

Franklin Street Extension

Update: Demolition of 62 W. Bridge Street is scheduled to begin Monday, March 28, in support of the Franklin Street extension project. Impact to traffic should be minimal and the project is expected to last the duration of the week. The timeline is subject to weather conditions. Demol
Continue Reading →

Shawan Falls Bridge Replacement

Crews will begin work on the Shawan Falls Bridge replacement project the week of March 21, 2022. There will be lane closures on Shawan Falls Drive north of Bridge Street Tuesday, March 22 through Friday, March 25, 7 a.m. – 5 p.m. for tree clearing activities. One lane, two-way traffic
Continue Reading →

Traffic Signal Work at Riverside Drive and Summit View Road

Riverside Drive and Summit View Road Crews are doing signal upgrade work on the traffic signals at the intersection of Riverside Drive and Summit View Road. Traffic Impact: Temporary lane closures on Riverside Drive at Summit View Road intersection between 7 a.m. – 6 p.m.  
Continue Reading →

Mooney Street Utility Installation

Installation of private utilities will close northbound Mooney Street between Bridge Park Avenue and Tuller Ridge Drive Mondays through Fridays. Northbound Mooney Street will be closed between Bridge Park Avenue and Tuller Ridge Drive Mondays through Fridays. Follow the posted detour.
Continue Reading →

Memorial Drive Tunnel Maintenance

The Memorial Drive tunnel project is now complete and the tunnel is open. Crews made significant improvements to the pedestrian tunnel between Dunniker Park Drive and Kilbirnie Court. The tunnel opened one week ahead of the contract completion date of May 17, 2019. The City thanks eve
Continue Reading →

Post Road Area Utility Work

This project is complete with no anticipated impact to traffic. Thank you for your patience.  
Continue Reading →

Deer Run Improvement Group 1

There is no scheduled work and no anticipated impact to traffic. ### Media contact: Andrew Kohn Public Affairs Officer 614.410.4508 – Desk 614.578.1302 – Cell akohn@dublin.oh.us Newsroom: https://dublinohiousa.gov/newsroom @DublinOhio | @DublinPolice | www.DublinOhioUSA.gov
Continue Reading →

The Corners

Private water line installation to be completed June 2022. Frantz Road will have temporary lane closures controlled by traffic control devices southbound between Paul Blazer Parkway and Rings Road from 9 a.m. – 4 p.m. The Corners is a mixed-use development project with public pa
Continue Reading →